+ | *Retried PCR of backbone for +8 magnesium riboswitch biobrick and fluoride biobrick at 60 °C and 64 °C. | ||
+ | |||
+ | *Verification gel showed that no bands of the appropriate size came out. Once more, only primer dimers produced. | ||
+ | |||
+ | *Production of primer dimers at these temperatures causes us to doubt that a successful PCR will be carried out at these temperatures. We may have to switch to ordinary ligation to construct our biobricks for submission. | ||
+ | |||
+ | '''[[Team:Cambridge/Protocols/PCRcolony|Colony PCR of biobrick containing colonies]]''' | ||
+ | |||
+ | ---- | ||
+ | |||
+ | *Gibson assembly of biobrick plasmid yesterday produced a few colonies. These were tested with the standard sequencing primers to check if an insert of the correct size had been introduced into the bacteria. | ||
+ | |||
+ | *Gel showed that fragments of the appropriate size were produced for one of the -8 biobricks and one of the -8 colonies. These will be grown up, miniprepped and sent for sequencing. | ||
===Wednesday (12/09/12)=== | ===Wednesday (12/09/12)=== |
Revision as of 00:44, 17 September 2012
Week: | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
---|
Contents |
Monday (10/09/12)
- Attempted to run PCR of the backbone for the biobricks once more. Settings: Annealing temperature: 56°C, elongation time: 30secs.
- After running on gel, saw that while the -8 vector amplification appears to be producing some correctly sized (~2kb) bands, the other two only seem to be forming many primer dimers. Analysis of the sequence of the prefix and suffix revealed a CG palindrome that appears to be causing self annealing. Inserts are not affected, as they have the palindrome at the 5' end of the primer.
- Will retry at higher temperatures tomorrow.
- Attempted Gibson assembly for the -8 magnesium riboswitch biobrick with the backbone fragments produced earlier today and the insert fragments produced yesterday.
Transformation of e.coli with Gibson products
- E.coli cells transformed with Gibson products produced earlier today.
- Transformants plated out on 25μ/ml chloramphenicol plates.
Tuesday (11/09/12)
- Retried PCR of backbone for +8 magnesium riboswitch biobrick and fluoride biobrick at 60 °C and 64 °C.
- Verification gel showed that no bands of the appropriate size came out. Once more, only primer dimers produced.
- Production of primer dimers at these temperatures causes us to doubt that a successful PCR will be carried out at these temperatures. We may have to switch to ordinary ligation to construct our biobricks for submission.
Colony PCR of biobrick containing colonies
- Gibson assembly of biobrick plasmid yesterday produced a few colonies. These were tested with the standard sequencing primers to check if an insert of the correct size had been introduced into the bacteria.
- Gel showed that fragments of the appropriate size were produced for one of the -8 biobricks and one of the -8 colonies. These will be grown up, miniprepped and sent for sequencing.